Home
Company
Profile
Projects
Pictures
Employment
Contact Us
Site Map
| |
Jay Dee Contractors, Inc.
Livonia, MI
Current Projects
Big Walnut
Augmentation/Rickenbacker Interceptor
Columbus, Ohio |
City of
Columbus, OH
|
This job is one of a
series of projects designed to increase the capacity of the City of Columbus sewer system. This
project consists of approximately 20,000 lft
of 14' I.D. tunnel. Tunnel excavation through boulder laden sand and gravel is
being performed by a 193" Lovat Earth Pressure Balanced Tunnel Boring Machine.
The tunnel is being lined with precast concrete segments. Other aspects of the
project include a large excavation box sever, a river crossing and several
access shafts and manholes.
Brightwater
Conveyance System
King County Washington |
King
County, WA
|
This west coast project, part of the Brightwater Conveyance
System adjacent to Puget Sound, c alls for construction of over 21,000 lft of 13' I.D.
tunnel in glacial till. The tunnel is to be lined with pre-cast concrete segments
with 2,500 lft to be lined with 10'
diameter steel pipe. tunnel that is lined. A portal structure and sampling facility
will also be constructed.
Dobson Run Flood
Relief Tunneling Project
Philadelphia, Pennsylvania |
City
of Philadelphia, PA Water Department
|
This project calls
for the rock excavation of approximately 3,600 lft of 12' 6" diameter cast in
place concrete storm water conduit. Diversion, Drop, Outfall and Transition structures
will also be constructed on this project.
Completed Projects
|
Romeo Arm Interceptor
Macomb Township, Michigan
|
City of Detroit
|
This
project included 16, 000 LFT of 84" diameter tunnel which was
excavated through
clay, silt, and hard pan. At an average depth of 40 feet, the
pipe-in-tunnel method of tunnel excavation was utilized with the
tunnel having a primary lining of ribs and lagging. A 125" Lovat
TBM was used for the excavation. The project also included two
meter structures and various smaller structures and shafts.
|
|
Thornton Transitional Reservoir
Thornton, Illinois
|
Metropolitan Water
Reclamation District of Greater Chicago
|
This project
included the excavation of tw o
different sized diameter tunnels. Excavation of unlined tunnels
included 7,900 LFT of 22' diameter and 2,700 LFT of 8' diameter
excavations through dolomite limestone. The project also included
two large underground structures and a diversion structure.
|
Calumet Tunnel System - Little Calumet Leg
South Holland, Illinois
|
Metropolitan
Water Reclamation District of Greater Chicago
|
This project
included approximately 19,000
linear feet of various sizes of
connecting sewer and entrance conduit structures varying in size
from 24 to 120 inches. This project included several drop and access
shafts
with diameters from 4 feet
to 15 feet and from 160 to 200
feet in elevation. Various other regulating structures were
also constructed. |
|
|
Rehabilitation
of Complexes A & B Sludge Thickeners and Associated Facilities
Detroit, Michigan
|
Detroit Water and
Sewerage Department
|
|
|
This rehabilitation project at the Detroit Wastewate r
Treatment Plant called for the overhaul of Sludge Thickening Complexes, Sludge
Storage Tank associated control buildings and
pipe galleries. This project required the skills of Process
Mechanical,
Electrical, HVAC, Instrumentation, Demolition and concrete trades.
This project required careful coordination with Plant Operations as
work was completed in an active Plant Setting. |
|
|
Cady Marsh Drainage Ditch
Griffith, Indiana
|
Department of
Army
|
|
|
|
Constructed to eliminate perennial area flooding, this project
consists of approximately one mile of 10' concrete lined tunnel
through silty clay. Several structures were built including inlet
and outlet structures, and both discharge and overflow weirs., |
|
|
Empire WWTP Outfall & Rosemount Interceptor
Phases II and III
Rosemount, Minnesota
|
Metropolitan
Council of Environmental Services
|
Approximately 4,700 lft of 66" diameter and 4,700 lft of
78" diameter pipe was placed in a tunnel using both the jack pipe and
rib and lag tunneling methods.
|
 |
|
|
Crosstown 8 Collector System
Milwaukee, Wisconsin |
Milwaukee
Metropolitan Sewerage District
|
|
|
|
5,150 lft of 108" sewer was constructed with one-pass concrete segmental lining.
Excavation was performed with a 126" Lovat Earth Pressure Balance Tunnel Boring
Machine through silty clays and saturated sands. Several junction and drop
structures were also built.
Richton Park Outlet
Richton, Illinois |
Metropolitan Water
Reclamation
District of Greater Chicago
|
10,030 lft of 60" sewer tunnel
was installed by the pipe jack method, using a Decker Tunnel Boring Machine.
The tunnel was lined with reinforced concrete pipe utilizing the jack pipe
tunneling method. The tunnel was excavated through soil conditions of
clay, silt, and boulders at an average depth of 27 feet. The longest
tunneling run on the project was 1,045 lft.
Center Street Relief
Sewer
Houston, Texas |
City of Houston, TX
|
Two Decker Tunnel Boring Machines were used to construct
16,778 lft of sewer tunnel utilizing both the jack pipe and rib and lag
tunneling methods. The mining took place at an average depth of 59 feet
through saturated sands and silts, and slickensided clays. The project
also included various junction structures. The longest tunneling run on
the project was 1,563 lft. Portions of the tunneling took place under the
White Oak Bayou.
Mobil Oil Company Refinery
Beaumont, Texas |
Mobil Oil Company / Bechtel
|
Located
within the Mobil Oil Refinery, this storm water separation tunnel consisted of
2,500 lft of 102" I.D. fiberglass pipe inside a 128" O.D. fabricated steel
liner. A 133" diameter Lovat Earth Pressure Balance TBM was utilized to
excavate through slickensided clays, saturated sands and silts. Two 60 ft
deep caissons were also constructed, one 25 feet in diameter and one 50 feet in
diameter. Since this was a "Design / Build" project, Jay Dee also provided
the design services.
Weller Creek Sewer
Arlington Heights, Illinois |
Village of Arlington Hts, IL
|
This
project consisted of 10,223 lft of 108" I.D. reinforced concrete pipe in tunnel
utilizing the pipe jacking tunneling method. The average tunnel depth was
58 feet with the average distance between shafts of 1,278 lft. Tunneling
was completed by means of a 131" diameter Earth Pressure Balance TBM through
clays, silt, and silty clays. Other major features included a large drop
shaft / deaeration chamber excavated in rock along with a connection to an
existing Deep Tunnel owned by the Metropolitan Water Reclamation District of
Greater Chicago.
Combined Sewer Overflow Control
Facilities
East Lansing, Michigan |
City of East Lansing,
MI
|
This
Combined Sewer Overflow project included 7,950 lft of 120" diameter tunnel in
boulder laden sands, glacial till, silts, and clay. A 159" Lovat Tunnel
Boring Machine was utilized. The project also included the demolition of
the Michigan State University Fisheries Facilities, as well as the construction
of a Wier / Baffle structure, pump station, and outfall. A large portion
of the project took place on the campus of Michigan State University.
West Fork Relief Sewer
Fort Worth, Texas |
City of Fort Worth, TX
|
Approximately
7,000 lft of 96" tunnel was constructed and 2,200 lft of opencut on this relief
sewer project. A 133" diameter Lovat TBM was used for excavating through
clachi shale soil conditions including river crossing near the Downtown section
of Fort Worth. Also included was 2,400 lft of 24" sewer installed by
microtunneling.
South Pennsylvania Avenue
Milwaukee, Wisconsin |
Milwaukee Metropolitan Sewerage District, WI
|
8,197 lft of 42" sewer in tunnel
was constructed by means of the jack pipe tunneling method. A 54" Decker
Tunnel Boring Machine was employed to excavate the tunnel through boulder laden
clays, silts and sands at an average depth of 37 feet.
Downriver Regional Storage &
Transport System
Southgate, Michigan
|
Wayne County, MI
|
This
Combined Sewer Overflow project for the County of Wayne, Michigan included
25,700 lft of 90" diameter tunnel excavated through soft clay laden with
boulders. At an average depth of 50 feet, the pipe-in-tunnel method was
employed wherein 90" diameter concrete pipe were placed inside the previously
excavated tunnel and grouted in place. The tunnel, excavated by a 125"
Lovat TBM, had a primary lining of ribs and lagging. The project also
included approximately 1,400 lft of smaller diameter tunnel and several
underground junction and control structures. Hydrogen Sulfide was
present in the groundwater for the entire duration of the tunneling operation.
Sarah Street Trunk Storm Sewer
Mishawaka, Indiana |
City of Mishawaka, IN
|
This
storm water project included 5,300 lft of 120" sewer tunnel with an outlet
transition structure and outfall into the St. Joseph River. The tunnel was
excavated by a 163" Lovat TBM and was supported with a primary liner of ribs and
lagging. The 120" final lining consisted of a monolithically cast-in-place
concrete.
Waste Water Treatment Plant
Bolingbrook, Illinois |
Village of Bolingbrook, IL
|
This project included the
construction of a building to house the secondary treatment facility.
Major items included an oxidation ditch, raw sewage pump station, two final
settling tanks, and sludge thickening and aerobic digestion components.
Waste Water Treatment Plant
Hanover Park, Illinois |
Village of Hanover Pk, IL
|
Construction of this new waste
water treatment plant included three 65 ft. diameter clarifiers, 130 ft.
diameter oxidation tank, ultraviolet disinfection facilities, grit removal
facilities, and a raw sewage pumping station.
Downriver Regional
Storage and Transport System
Wyandotte, Michigan |
Wayne County, MI
|

This tunnel pump station project
was constructed utilizing the caisson construction method. The 50 ft.
diameter caisson houses several high capacity sewage and chopper pumps.
Buildings for both the electrical and mechanical equipment were also
constructed. Site and civil work included concrete paving, storm and
sanitary sewers and temporary sheeting. Miscellaneous off-site tunnel and
basin work including instrumentation and control provisions was also completed.
Top of Page
| |
|